Contract: Tender floated for well drilling and other auxillary
operations – Work order awarded to appellant – During subsistence
of contract, prices of High Speed Diesel (HSD) one of the essential
materials for carrying out the drilling operations increased through
a circular issued by Government – Appellant raised a claim that
increase in the price of HSD triggered the ‘change in law’ clause
contained in clause 23 under the contract and the respondent
became liable to reimburse them for the same – In terms of Clause
23, if subsequent to the date of price of Bid Opening, there was a
change in or enactment of any law or interpretation of existing law,
which resulted in additional cost/reduction in cost to contractor on
account of the operation under the contract, the contractor would
be entitled to receive such additional/reduced cost actually incurred
– Appellant invoked the arbitration clause – Arbitral Tribunal
allowed the claim holding that Clause 23 must be liberally construed
and any circular of the Government would amount to a change in
law – On appeal, High Court set aside the award – Held: There are
price fluctuations which a prudent contractor would take into
margin, while bidding in the tender – Such price fluctuations cannot
be brought under ‘change in law’ clause unless specific language
points to the inclusion – The contract in question was based on a
fixed rate – The party, before entering the tender process, entered
the contract after mitigating the risk of such an increase – The
interpretation of Arbitral Tribunal to expand the meaning of Clause
23 to include change in rate of HSD was not a possible interpretation
of this contract as the appellant did not introduce any evidence to
prove same – Arbitral award set aside – Contract Act – s.56 –
Arbitration and Conciliation Act, 1996 – s.34 – Doctrine of Force
Majeure.
Arbitration and Conciliation Act, 1996: s.34 – Scope of court’s
jurisdiction under s.34, discussed.