[2015] 1 S.C.R. 627
M/S. KAILASH NATH ASSOCIATES
v.
DELHI DEVELOPMENT AUTHORITY & ANR.
(CivilAppeal No. 193 of 2015)
JANUARY09, 2015
[RANJAN GOGOi AND R.F. NARIMAN, JJ.]
ContractAct, 1872-Publicauction-Earnestmoney -
Forfeiture
of - Appellant,highest bidder for plotdeposited 25%
A
B
of the bid amount-earnestmoney (Rs 78 lakhs) with ODA - C
Balance75% was to bedepositedwithin three months-
Extension
of timefor payment by DOA twice-Thereafter,
severalletters writtenby
the appellant to DOA but no response
- Subsequently,letter writtenby
ODA to the appellantthat his
casewas referred
to UOI for its approvalfor condoningthe D
delay, case beingone of Nazulland, whichwas laterdeclared
by the CentralGovernmentas non-Nazulland - On DDA's
request,
appellant consentedto making payment of the
balanceamount with interestcharged-
After few years
cancellation of allotment of the plotby ODA andconsequent E
forfeiture of the earnestmoney - Suit for specificperformance
and damages and recovery of earnest amount by the'
appellant-Subsequently DOA re-auctionedthe premises
fetching
Rs. 11. 78 crores-Dismissal of suitby the Single
Judge of theHighCourtbut orderedrefund of the earnest F
moneyforfeitedwith 9% interest p.a. -However,Division
Benchupheldforfeiture
of the earnestmoney - On appeal,
held:It wasarbitraryfor the
DOA to forfeitthe earnestmoney
-
In theabsence of notice to depositthe balance 75% amount
withina certainstated
time, there is nobreach of contract on G
the part of theappellantand consequentlyearnest money
couldnot be forfeited-
ODA not havingbeen put to anyloss,
even
if ODA couldinsist on a contractualstipulation in its
favour,it wouldbe arbitrary
to allow DOA as a publicauthority
627 H
628 SUPREME COURT REPORTS [2015] 1 S.C.R.,
A to appropriate Rs. 78 lakhs withoutany loss being caused-
Article
14 wouldapply - In fact, DOA madehuge profit on re
auction
of theplot- If damage or loss is notsuffered,the law
doesnot providefor a windfall-
Thus, the judgment of the
Single Judge of theHighCourtrestored-Constitution of
B India,1950 -Article 14.
s. 7 4 - Compensation for breach of contractwhere
penalty stipulated for under - General principles -
Enunciated.
CAllowing the appeal,the Court
HELD: 1.1. Theearnestmoney can be forfeitedunder
sub-clause(iv)
of the conditions of auction, only in the
case
of default,breach, or non-compliance of any of the
o terms and conditions of the auction, or on
misrepresentationby thebidder.The balance 75% which
had to be paid within three months of the acceptance of
the bid, was not insisted upon by the DOA.On the
contrary,after settingup two High PoweredCommittees
E
which were instructed to look into thegrievances of the
appellant, the DOA extended time at least twice. It is,
therefore,very
difficult to say that therewas a breach of
anytermsand conditions of the auction,as theperiod of
three months which the DOA could haveinsisted upon
F had specifically been waived. It is nobody's case that
thereis anymisrepresentationby thebidder.Therefore,
under sub-clause(iv), without more, earnestmoney could
not have beenforfeited.[Para 15] [643-B-D]
1.2.
Long after the Central Government informed
G ODA (on 1.3.1990) that the property involved "in the
instant case is not Nazulland, the ODA by its letter of
6.10.1993 cancelled the allotment of the plot becausethe
appellant had failed to deposit the balance75%. DDA's
understanding, therefore, was that what was important
H
KAI LASH Nfo:TH ASSOCIATES v. DELHI DEVELOPMENT 629
AUTHORITY
was payment of the balance 75% which was insisted
upon by the letter and which was acceded to by the
respondent immediately on the same date. Further it
cannot be accepted that since the letter was "without
prejudice" and since no commitmenf hadbeenmade,
theywere
not boundby theterms of the letter. The letter
was without prejudice and no commitment could have
beengivenbythe ODAbecausethe
Central Government
may
well not relax the NazulRules.On the otherhand, if
A
B
the Central Governmenthad, later on, relaxed the Nazul
Rules,
DOA could not beheardto say that despite this c
havingbeen done,DOA would yet cancel the allotment
of the plot.Thatthis could not havebeendoneis clear
because of the construction of the letter and also
because DOA is a public authority boundby Article 14
and
cannot behave arbitrarily.[Para 17] [644-A-E]
1.3.The
Single Judgewas correctin observing that
D
the letter of cancellation dated6.10.1993and consequent
forfeiture
of earnestmoney was made without puttingthe
appellant on notice that it has to depositthe balance 75%
premium
of the plot within acertainstated time. In the E
absence
of suchnotice,there is no breach of contract on
thepart
of the appellant and :Onsequently earnestmoney
could not be forfeited. It would bearbitrary for theDOA
to forfeit the earnest money on two fundamental
grounds.First, thereis no breach of contracton thepartF
of the appellant. And second,ODA not having been put
to any loss, even if DOA could insist on a contractual
stipulation in itsfavour, it would bearbitrary to allow DOA
as a public authority to appropriate Rs.78,00,000/
(RupeesSeventy Eight Lakhs) without any loss being G
caused.Therefore,
Article 14 would apply in the field of
contract in theinstantcase. [Para 21, 29][645-E-F;651-
H; 652-A-B]
1.4.As earnest
money is an amount to be paid in
case of breach of contract andnamedin the contract as H
630 SUPREMECOURT REPORTS [2015) 1 S.C.R.
Asuch, it would necessarily be coveredby Section 74. In
cases wherea public auctionis held, forfeiture of earnest
money may take place even before an agreement is
reached,as ODAis to acceptthe bid only afterthe earnest
moneyis paid.
In theinstantcase, underthe termsand
Bconditions
of auction,the highestbid (along with which
earnest money has to be paid) may well have been
rejected. In such cases, Section 74 may not be attracted
on
its plainlanguage because it applies only "when a
contracthas beenbroken".
In the instantcase, forfeiture
c of earnestmoney took place long after an agreementhad
beenreached.
It is obviousthat the amount sought to be
forfeitedon thefacts
of theinstantcase is sought to be
forfeited without any loss being shown. In fact it has
been
shown that far from suffering any loss, DOAhas
0 receiveda much higher amounton re-auction of thesame
plot of land. [Para 40, 41, 42) [663-G-H;664-A-D]
E
F
G
H
1.5.The law on compensation for breach of contract
under Section 74 canbe stated to be as follows:-
1. Wherea sumis namedin a contractas a liquidated
amount payable by way of damages, the party
complaining of a breachcan receiveas reasonable
compensation such liquidated amount only if it is a
genuine pre-estimate of damages fixed by both
partiesand found to be suchby theCourt. In other
cases,
where a sum isnamedin a contract as a
liquidated amount payable byway of damages, only
reasonable compensation can be awarded not
exceedingthe amount so stated. Similarly, in cases
wherethe
amount fixed is inthenature of penalty,
only reasonable compensationcan be awarded not
exceedingthe penalty so stated. In both cases,the
liquidated amount or penalty is the upper limit
beyond which the Court cannot grant reasonable
compensation.
KAILASH NATH ASSOCIATES v. DELH(DEVELOPMENT 631
AUTHORITY
2. Reasonable compensation would be fixedon well A
known principles that are applicable to the law of
contract, which are to be found inter alia in Section
73 of the Contract Act.
3. Since Section 74 awards reasonable 8 compensation for damage or loss caused by a
breach
of contract,damage or loss caused is a sine
quanon
for the applicability of theSection.
4. Section applies whether a personis a plaintiff or a
defendantin a suit.
C
5. The sum spoken of may already be paid or be
payable infuture.
6. The expression "whether or not actual damage or 0 loss is proved to havebeencaused thereby" means
that where it is possible to proveactualdamage or
loss, such proof is not dispensed with. It is only in
caseswheredamage
or loss is difficult or impossible
to prove that the liquidated amount named in the
contract, if a genuinepre-estimate of damage or loss, E
can be awarded.
7. Section 74 would apply to cases of forfeiture of
earnest money under a contract. Where, however,
forfeiture .. takes place under the terms and conditions F
of a public auction before agreement is reached,
Section 74 would have no application. [Para 43][664-
D-H; 665-A-F]
1.6.TheDivisionBench has
gone wrong in principle.G
Therehas been
no breach of contract by the appellant.
Further,the view of the Division Bench that the fact that
the ODA madea profit from re-auction is irrelevant, as
that would fly in theface of the most basic principle on
theaward
of damages- namely, that compensation can
only be given for damage or loss suffered cannot be H
632 SUPREME COURT REPORTS [2015] 1 S.C.R.
A accepted. If damage or lossis not suffered,the law does
not provide for a windfall.The judgment and order of the
Single Judge is ~estored. [Para 44, 47][665-G-H;666-A,
E]
8 Shree HanumanCotton Mills & Anr. v. Tata Aircraft Ltd.
1970 (3) SCR 127; Anandram Mangturam v. Bholaram
Tanumal, ILR 1946 Born 218; Keshav/alLallubhai Patel and
Ors. v. La/bhaiTrikumla/Mills Ltd 1959 SCR 213; Citi Bank
N.A. v. StandardCharteredBank 2003 (4) Suppl. SCR 489:
C (2004) 1 SCC Page 12; S. Brahmanand v. K.R. Muthugopal
2005 (4) Suppl. SCR 461 :(2005) 12 SCC 764; TP. Daver
v. LodgeVictoria No. 363, S.C. Belgaum 1964 (1) SCR 1;
ABL International Ltd. v. ExportCredit GuaranteeCorpn. of
India Ltd. (2004) 3 SCC 553; Fateh Chand v. Balkishan Das
1964 SCR (1) 515; Mau/aBux v. Union of India (UOI) 1970
D (1) SCR 928; Shree HanumanCotton Mills and Anr. v. Tata
AircraftLimited 1970 (3) SCR 127; ONGC Ltd. v. Saw Pipes
Ltd 2003 (3) SCR 691: (2003) 5 SCC 705 - referredto.
Tilley v. Thomas, (1867 3 Ch.A 61); Webb v. Hughes,
E V.C.M. 1870 - referredto.
Case
Law Reference:
1970 (3) SCR 127 Referred to Para 14
F ILR 1946 Born 218 Referred to Para 19
1959
SCR 213 Referred to Para 24
2003 (4) Suppl.SCR 489 Referred to Para 25
2005 (4) Suppl. SCR 461 Referred to Para 26
G 1964 (1) SCR 1 Referred to Para 28
(2004) 3 sec 553 Referred to Para 28
1964
SCR (1) 515 Referred to Para 33
H 1970 (1) SCR 928 Referred to Para 35
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 633
AUTHORITY
1970 (3) SCR 127
2003 (3) SCR 691
Referred to
Referredto Para 36
Para 37
CIVIL APPELLATE JURISDICTION:Civil Appeal No. 193
of
2015.
Fromthe Judgment & Order dated 28.05.2012 of theHigh
Court
of Delhi atNew Delhi in RFA (OS) No. 10 of 2008 in CS
(OS)
396of 1994.
A
B
ParasKuhad, Manmeet Arora,Kaveeta Wadia, Vipin
Tyagi, Apporv Tripathi, Shashank Tripathi, Jatin for the C
Appellant.
Amarendra Sharan, DhruvTamta,Binu Tamta,Rekha
Pandey,
S. Ush,a Reddy, SushmaSuri for theRespondents.
TheJudgment
of the Courtwas delivered by
R.F. NARIMAN, J. 1. Leavegranted.
D
2. Thepresent appeal arises out of a public auction
conductedby the
DelhiDevelopment Authority ("ODA") whereinE
the
appellant madethe highestbid for Plot No.2-A,Bhikaji
Cama Place, District Centre, New Delhi for 3.12 Crores
(RupeesThree Crores Twelve Lakhs).As perthe termsand
conditions
of theauction,the appellant, being the highest
bidder,depositeda sum
of Rs.78,00,000/- (Rupees Seventy F
EightLakhs),being 25%
of the bid amount,with the ODA, this
beingearnestmoney under the terms
of theconditions of
auction.The relevant provisions in the conditionsof auctionread
as
follows:
"(ii)
Thehighestbidder shall, at the fall ofthehammer,pay G
tothe
DelhiDevelopment Authoritythrough the officer
conductingthe auction,25%
of the bid amountas earnest
moneyeither
in cash or byBankDraft in favourof the Delhi
Development Authority, or Cheque guaranteed bya
Scheduled Bankas "good for paymentfor three months" H
634 SUPREME COURT REPORTS [2015] 1 S.C.R.
A in favour of the Delhi Development Authority. If the earnest
moneyis notpaid,the auction
held in respect of that plot
will
be cancelled.
B
c
D
E
F
(iii)Thehighestbid shall be subjectto theacceptance of
Vice-Chairman, DOA or suchotherofficer(s)as may be
authorizedby himon his
behalf. Thehighestbid may be
rejectedwithout assigningany reason.
(iv)
In case of default, breachor non-compliance of any of
the terms and conditions of the auction or mis -
representationby thebidderand/or intendingpurchaser,
theearnestmoney shall be forfeited.
(v)The
successful biddfr shall submit a dulyfilled-in
application
in theformattachedimmediatelyafter the close
of the auction of plot in question.
(vi)Whenthe bid is acceptedby the
DOA, theintending
purchaser
shall beinformed of suchacceptance in writing
and
tbe intendingpurchaser shall, within 3 monthsthereof,
pay
to the DelhiDevelopment Authority,the balance 75%
amount
of thebid,in cashor byBankDraft in favour of
the Delhi Development Authorityor byCheque guaranteed
bya
Scheduled Bankas "good for paymentfor three
months" in favour of the Delhi Development Authority. If the
bidis notaccepted,the earnestmoney
will be refunded
totheintendingpurchaserwithout any interest
unless the
earnestmoney is forfeitedunder para 2 (iv)
above."
3. On 18.2.1982,the DOA acknowledged the receipt of
Rs.78,00,000/- (Rupees Seventy EightLakhs),acceptedthe
G
appellant's bidand directed the appellant to deposit the
remaining75% by 17.5.1982.However, as therewas a general
recessionin theindustry,the appellant and persons similarly
placed made ·representations sometime in May, 1982 for
extendingthe timefor payment of theremainingamount. The
DOA set up a HighPoweredCommitteeto look into these
H
KAILASH NATH ASSOCIATES v. DELHI DEVELOPMENT 635
AUTHORITY [R.F. NARIMAN, J.]
representations. The HighPoweredCommittee on 21.7.1982A
recommendedgranting the extension
of timeto biddersfor
depositingthe remainingamount
of 75%. Based on the High
PoweredCommittee'sreport, by a letterdated11.8.1982,the
ODA extended tjme for paymentupto 28.10.1982with varying
ratesof intereststartingfrom 18% and goingupto 36%.B
4. Another High PoweredCommitteewas also set up by
theDOA
in orderto findout whetherfurther time should be given
tothe
appellant andpersons similarly situateto the appellant.
5. ThesecondHigh PoweredCommitteerecommended C
that the time for payment be extended and specifically
mentioned the appellant's name as a personwho shouldbe
givenmore time to paythe balanceamount.Despite the fact
that
on 14.5.1984the ODAacceptedthe recommendations of
thesecondHigh PoweredCommittee,nothing happened till 0 1.12.1987. Several letters had beenwrittenby the appellant to
ODAfrom1984to 1987but no answerwas forthcoming
by the
ODA.
6. Videa letterdated1.12.1987,which is animportant
letteron thebasis
of whichthe fate of thisappeallargelyE
depends,the DOAstatedas
follows:
"WITHOUTPREJUDICE'
DELHI
DEVELOPMENT AUTHORITY
VIKASSADAN
l.N.A.F
No. F.32(2)/82/lmpl.-l/4
From: DIRECTOR (C.L) New
Delhi-23...... 198 ...
DELHI DEVELOPMENT AUTHORITY
To,
M/s.KailashNath & Associates,
1006, KanchanjangaBuilding,
18,BaraKhambaRoad,
New
Delhi-110001.
G
Sub: Regardingpayment of balance premium in respectH
A
B
c
D
E
F
G
H
636 SUPREME COURT REPORTS[2015] 1 S.C.R.
of Plot No.2-A situatedin BhikajiCama Place Distt.
Centre.
Sir,
Withreferenceto theabovesubject,
I am directedto inform
youthatyourcasefor
relaxing the provisions of Nazul
Rules,
1981,to condonethe delay for thepayment of
balancepremium in installmentswas referredto theGovt.
of India,Min. of Urban Development.Before the caseis
furtherexaminedby the
Govt. of India,Min. of Urban
Development,you are requestedto giveyourconsentfor
making
payment of balance amount of 75%premium
withinthe periodas maybe fixedalongwith18% interest
chargesp.a. on thebelatedpayment.Further the schedule
of payment and conditions if any will beas per the
directionsissued by theMinistry of Urban Development,
Govt.
of India. It is,however,made clear that this letter
doesnot carryany commitment.
Yourconsentshould reach to thisofficewithin3 daysfrom
thedate
of issue of thisletter.
Dated1.12.87
Yours faithfully,
Sd/
DIRECTOR(C.L)"
7. Theappellant replied to thesaidletteron thesame day.
itself in thefollowingterms:
"KAILASH NA TH & ASSOCIATES
Tel.:
3312648,3314269
1006, KANCHENJUNGA,
18, BARAKHAMBA ROAD,
NEW DELHl-110001
Regd.Ack. Due.
' KAI LASH !NATH ASSOCIATES v. DELHI DEVELOPMENT 637
AUTHORITY [R.F. NARIMAN, J.]
December 1, 1987.
The Director (C.L.),
Delhi Development Authority,
VikasSadan,
l.N.A.,
New Delhi-I10023.
Subject: Payment of balance premium in respect of
plot No.2-ABhikaji Gama Place Distt. Centre, New
Delhi.
Dear Sir,
A
B
c We are thankful to youfor your letter No. F.30(2)/82-lmpl.-
l/4
dated nil receivedby us thisafternoon,on theabove
subject.
We hereby give our consent that we shall make the
payment of the balance amount of 75%premiumwithin the D
period
as may befixedas per the schedule of payment
and
conditions, if any imposed, as per the directions
issuedby theMinistry of Urban Development,Govt. of
India, alongwith 18% interestcharges per annum on the
belated payment.E
We now request you to kindly convey us your formal
approval to ourmakingthe saidpaymentin installments
as requestedfor.
Thankingyou,
Yours
faithfully
For KAILASH NATH & ASSOCIATES,
Sd/
Partner
Advance copy sent through SpecialMessenger."
8. The Central Governmentinformed the DOA vide a letter
dated 1.3.1990 that the land auctionedto the appellant was not
Nazulland and, therefore,the Central Government would have
nothing
further to do withthe matter. Meanwhile, the appellant
F
G
H
638 SUPREME COURT REPORTS[2015] 1 S.C.R.
AfiledWrit PetitionNo.2395of
1990 in the Delhi High Court in
whichit claimed that persons similar to theappellant, namely,
Mis. Ansal Propertiesand Industries Private Limitedand M/s
SkipperTower PrivateLimitedhad been
allowed to paythe
balance 75%premiumand were in fact allotted other plots.
B PleadingArticle 14, the appellant stated that theywere entitled
to thesametreatment.
9. By a judgmentand orderdated2.9.1993,the Delhi
High Court held that as theauctionwas held as per termsand
Cconditionsof theauction,a disputeregardingthe same
is a
matterof contractand cannotbe goneinto
in proceedings
under
Article 226 of theConstitution. It wasfurtherobserved
that
on facts,the Courtfound no force in the contentionraised
on behalf of the appellant regardingdiscrimination.An SLP
Dagainstthis orderwas
also dismissed on 16.12.1993 by the
SupremeCourt statingthat the
appellant is at liberty totake
whateversteps are permittedto the
appellant under law to
challenge forfeiture of earnestmoney, which had beendone by
a letter of 6.10.1993.This letter is also important for thecorrect
determination
of this appeal andis setout hereinbelow:-
E
F
G
H
"REGD.A.D.
DELHI
DEVELOPMENT AUTHORITY
VIKAS
SADAN
1.N.A.
New Delhi-23, 6.10.1993
No.F.32(2)/82/CL/3816
From:
DY. DIRECTOR (CL).
To,
M/s. Kailash Nath& Associates,
1006, Kanchanjanga Building,
18,BaraKhambaRoad,
New
Delhi-110001.
Subject: Plot No.2-A in BhikajiCama Place Distt. Centre.
Sir,
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 639
AUTHORITY [R.F. NARIMAN, J.]
Consequent upon your failureto depositthe balance75% A
premium
of theaforesaidplot anddismissalof C.W.P. No.
2395 of 1990by theHon'bleHigh Court,Delhi, I am
directedto inform
you thatthe bid/allotmentof thesaidplot
in yourfavourhas beencancelledand earnestmoney
amountingto
Rs.78,00,000/- deposited by you at thetimeB
of auctionhas beenforfeited.
Yours faithfully,
Sd/
(JAGDISH CHANDER) c
DEP.UTY DIRECTOR(CL)"
10.
Theappellantthen filed a suitfor specificperformance
on17.2.1994and
in the alternativefor recovery of damages
andrecovery
of the earnestamountof Rs.78,00,000/- (Rupees
SeventyEight Lakhs).Shortly after the suitwasfiled,on D
23.2.1994,the DOAre-auctionedthe premiseswhich fetched
asum
of Rs.11. 78 Crores(RupeesEleven Crores Seventy
EightLakhs).
11.Thelearned
Single Judge by a judgmentand orderE
dated
10.9.2007 dismissedthe appellant's suit for specific
performanceand damagesbut orderedrefund of theearnest
moneyforfeitedtogetherwith 9% per annuminterest.The
learned
Single Judgeheld:-
"65. Defendant No. 1 instead of followingthe aforesaid F
course,found merit in the representationsreceived not
onlyfromthe plaintiffbut suchsimilar situatedparties. It
is in view thereofthat the matterwent as far as setting up
of two committees to repeatedlyexamine the matterand
to come to a conclusion. The case of defendant no. 1 was G
thatthe material produced by the plaintiff andsuch
similarpersonsgave
rise to a cause to extend the time
formakingthe paymentsubject
to certain terms and
conditions. However,in view of the perception of
defendant no.1 that the consent of UOI, defendantno.2, H
A
B
c
D
E F
G
H
640SUPREMECOURT REPORTS [2015) 1 S.C.R.
would be required,the landbeing Nazul land, the file was
forwarded
to defendant no. 2. The matterdid notrestat
thissincethereafter
UOI did grantsuch consentbut sent
backthe file
of the plaintiffonly on account of the factthat
theland
in question was notNazul land. The neteffect
of thisis thattherewas no permissionrequired from the
UOI and the decisiontaken by defendant no. 1 to extend
thetimeperiodfor makingthe payment,
thus, stood as
it is.
-66. In my considered view, it is notopenfor defendant
no. 1 to statethat whileit recommendedthe case of other
similarlysituated parties in
case of Nazul land to the
Government and obtained permission for grant of
extension of time, in case of non-Nazulland wheresuch
permissionwas not required,
a differentparameterwas ·
required to be followed. It maybe mentionedat thecost
of repetition that the plaintiff wasa party which
volunteeredto pay interest @18% per annum unlike
some
of theotherparties.There is merit in the contention
of learnedCounselfor theplaintiffthat defendant no. 1
aftertreatingthe contract
as subsistenthaving extended
timefor makingthe paymentwas at leastrequired
to give
a notice to the plaintiff to performthe agreementprior to
terminatingthe agreement ~:wd couldnot straightaway
terminatethe
same. This conclusioncan drawstrength
fromthe observationsin HalsburyLaws
of England
(supra)referred
to aforesaid as also in Webb v. Hughes
(supra).It isclearly
a case wherethere has beenwaiver
of the timebeingessence of the contractby conduct of
theparties and, thus,defendant no. 1 wasrequired to give
notice
on thedayappointedfor completion of thecontract
failingwhich only terminationcould take place.
67. Therewere numerouscommunicationsexchanged
betweenthe parties.
The recommendations of thetwo
high-poweredcommittees constituted
by defendant no. 1
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT641
AUTHORITY [R.F. NARIMAN, J.]
madeits recommendationswhich were
accepted by A
defendant no. 1 videits resolutiondated 14. 5. 1984 (Ex.
DW2/P-4). Having accepted the recommendations, in the
case of the plaintiffdefendant no. 1 wasrequiredto do
nothing further but mistakenly·referredthe case to UOI
for its approvalassumingthe case to be one of Nazul B
land.Plaintiffsent repeatedremindersvide lettersdated
9-12-1985 (Ex.P-11),20-10-1986 (Ex.P-12), 10-12-
1986(Ex.P-13),10-02-1987 (Ex.P-14), 11-04-1987(Ex.P-
16),10-08-1987(Ex.P-17)and 10-10-1987(Ex.P-18)
calling upon defendant no. 1 to give an offer of deposit of c
balance 25% of the premium so as to bringthe total
paymentequivalent
to 50% of the total premiumand for
release
of thepossession of the land to theplaintifffor
purpose
of construction.Defendant no. 1 videits letter
receivedon 1.12.1987
by theplaintiff(Ex.P-19)sought D
the consent of the plaintiff to abide by the
recommendations
of thehigh-poweredcommittee and
theconsentwas dulygiven
on the evendate (Ex.P-20).
Thereafterno offerwas made
to the plaintiffand without
any notice of.compliance for payment,the letter of
cancellationdated 6.10. 1993(Ex.P-26)was issued.It E
appearsthat defendant no. 1 itselfwas not aware of the
landbeingnon-Nazulland
as the firstcommunication
wasaddressed
to the plaintiffonly on 1.3.1990.
68. The presentcase is one wheredefendant no. 1 has F
not evensuffered a loss. The plot was to be purchased
by theplaintiffat Rs. 3. 12 crores and it wasfinallysold to
a third partyat Rs. 11.78crores, i.e. almostthree and a
half timesthe price.Duringthis perioddefendant no. 1
continued
to enjoythe earnestmoney of the plaintiff of G
Rs. 78.00 lacs.
69.In
view of the prolonged period, exchange of
communications,the plaintiffmaking variousoffers but
notcomplyingwith the initialterms,defendant
no. 1 taking H
642 SUPREME COURT REPORTS [2015] 1 S.C.R.
A its owntime in the decisionmaking process,I am of the
consideredview that
the plaintiffis entitled to therefund
of theearnestmoney of Rs. 78.00 lacs but no further
amountis liable
to bepaid to the plaintiff."
B 12. DOA appealed againstthe Single Judge'sjudgment
to a DivisionBench of the Delhi High Court._The DivisionBench
setasidethe judgmentof the
Single Judge holding thatthe
forfeitureof theearnestmoney by the
ODA was in order.
· 13. Shri ParasKuhad, learned SeniorAdvocateappearing
C on behalf of the appellant, urgedthat timemay have be-en of
theessenceunder the
original termsand conditions of the
auction.However,time had beenextended
on several
occasionsand, therefore,ceased to be of theessence. In
answer to the letter dated1.12.1987,the appellant promptly
D replied and said it would be willing to pay the entire 75% with
18%interestand, therefore,there was no breachof contract
on thepartof the appellant. Further,since the ODA sold the
plot for 11.78Crores(Rupees Eleven Crores SeventyEight
Lakhs),there was no
loss causedto the DOA and,hence
Eforfeitureof earnestmoney
would not be in accordancewith the
agreement or in accordancewith law.
F
14. Shri AmarendraSharan, learned Senior Advocate
appearing
on behalf ofthe ODA, rebuttedthese contentions
and addedthat the case was covered by the judgment in Shree
HanumanCotton Mills & Anr. v. Tata Aircraft Ltd., 1970 (3)
SCR 127. He argued further that sincethe letter of 1.12.1987
had been issuedunder a mistakeof fact, it would be voidunder
Section
20 oftheContractAct andthe said lettershould,
therefore, be ignored. If it is ignored,then the terminationof the
Gcontract
and the forfeitureof earnestmoney are completely in
order as the appellant was in breach.The fact thatthe ODA
ultimatelysold the plot for a much larger sum,accordingto
learned counsel,would be irrelevant inasmuchas the
contractual term agreedupon betweenparties would entitle him
H
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 643
AUTHORITY [R.F. NARI MAN, J]
to forfeit earnestmoney on breach withoutany necessityof A
proving
actualloss.
15. Havingheard learnedcounsel for theparties,it is
important at the veryoutsetto noticethat earnestmoney can
be forfeitedunder sub-clause (iv) set outhereinabove, only in B
thecaseof
default, breach,or non-compliance of anyof the
termsand conditionsof theauction,or
on misrepresentation
bythebidder.
It may be notedthat the balance 75%which had
to be paid withinthree monthsof theacceptanceof the bid, was
notinsistedupon
by the DOA. On the contrary,after setting up C
two HighPoweredCommitteeswhich were instructedto look
into the grievancesof theappellant,the DOA extended time at
least twice. It is, therefore,very difficult to say thattherewas a
breachof
any terms and conditionsof theauction, as the period
ofthreemonthswhich the
ODA could have insistedupon had
specificallybeen waived. It is nobody'scase that there is anyD
misrepresentationhere
by the bidder.Therefore,under sub
clause (iv), withoutmore, earnestmoney could not havebeen
forfeited.
16. The other noticeable featureof thiscase on facts is E
that
DOA specificallyrequested the appellant to givetheir
consentto makethe
balancepayable along with 18% interest
charges
on belatedpayment.This was on the footingthat the
Nazul Rules of 1981 would be relaxedby the Central
Government.The rea·son why the letter is marked "without F
prejudice" andthe DOAmadeit clear that the letterdoesnot
carryany commitment,is obviouslybecause the
Central
Governmentmay not relax the provisionof the NazulRules, in
whichcase nothingfurther could be doneby the DOA.If,
however, the Central Governmentwas willing to condonethe G
delay, ODA would be willing to take 75% of theoutstanding
amount
along with18%interest.
17. Mr. Sharan arguedthat sincethe Central Government
ultimately foundthat this wasnot a Nazulland, the letterwas
obviously based on a mistakeof factand would be voidunderH
644 SUPREME COURT REPORTS [2015] 1 S.C.R.
A Section 20 of the ContractAct. We are afraidwe arenot able
to acceptthis plea. Long after the Central Governmentinformed
ODA(on 1.3.1990)that the property
involved in the present
caseis not
Nazulland, the ODAby its letter of 6.10.1993
cancelled the allotment of the plot becausethe appellant had
B
failed todepositthe balance 75%. DDA'sunderstanding,
therefore,was that whatwas importantwas payment
of the
balance 75%whichwas insistedupon by the letter dated
1.12.1987and whichwas accededto bytherespondent
immediately on the samedate. Further, Mr. Sharan'sargument
c theai since the letterwas "withoutprejudice" and sinceno
commitmenthad beenmade,they werenot bound
by theterms
oftheletteralso fails to impress
us. Theletterwas without
prejudiceand
no commitmentcould have beengiven by the
ODAbecausethe
Central Governmentmay well not relaxthe
0Nazul
Rules.
On the otherhand,if the Central Governmenthad,
lateron, relaxedthe NazulRules,
DOA could not be heardto
saythatdespitethis havingbeen done,
ODA wouldyet cancel
the
allotment oftheplot.Thatthis couldnot havebeendone is
clearbecauseof theaforesaidconstructionof theletterdated
E
F
G
H
1.12.1987and alsobecauseDOA is a publicauthoritybound
byArticle
14 andcannotbehavearbitrarily.
18.
It nowremainsto dealwith the impugnedjudgment of
theDivisionBench.
19. The Division ·Benchfollowed the judgmentof Tilley v.
Thomas, (1867 3 Ch.A 61) anddistinguishedthe judgment in
Webb v. Hughes, V. C. M. 1870.It furtherwent on to follow
AnandramMangturam v. Bholaram Tanumal, ILR 1946 Born
218andheld:
"The decisionholds that the principle of law is that where,
by agreement,time is made of the essence of the
contract,it cannot
be waivedby a unilateralact of a party
andunlessthere
is consensusad-idem betweenthe
partiesand a newdate
is agreed to, merelybecausea
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 645
AUTHORITY [R.F. NARIMAN, J.]
party to a contractagrees to considertime beingextended A
-for the opposite party to completethe contract, but
ultimatelyrefuses to accord concurrencewould not mean
thatthe partyhas
by conductwaived the dateoriginally
agreed
as being of theessence of the contract." (At para
3~ B
20. In our judgment, Webb's casewoulddirectlyapply to
thefactshere.
In that case,it was held:
"But if timebe madethe essence of thecontract,
thatmay
be waived by the conduct of the purchaser;and C
if the timeis once allowed to pass, and the partiesgo on
negotiatingfor completion
of thepurchase,then time is
nolonger
of theessence of the contract. But, on the other
- hand,
it mustbe borne in mindthat a purchaseris not
bound
to waitan indefinitetime; and if he finds,while the D
negotiationsare going on, thata long time;,Will elapse
beforethe contractcan be _completed,he
may in a
reasonablemanner give notice
to the vendor,and fix a
periodat whichthe businessis
to be terminated."
21.Basedon thefacts of thiscase, the_ Single Judge was
correct in observing that the letter of cancellation dated
6.10.1993 andconsequentforfeiture of earnest money was
made without putting the appellant on notice that it hasto
depositthe balance75% premium
of the plotwithina certain
statedtime.
In the absence of suchnotice,there is nobreach
ofcontract
on thepart of the appellant andconsequentlyearnest
money cannot be forfeited.
22.
Tilley v. Thomas, (18673 Ch.A61) would not apply
E
F
for thereason thatthe expression "without prejudice"was only G
usedas statedabovebecausethe CentralGovernmentmay
not
relax the NazulRules.
23. In AnandramMangturam v. Bholaram Tanumal, ILR
1946 Born 218, two separatejudgmentswere delivered, one
H
A
B
c
D
E
F
G
H
646 SUPREME COURT REPORTS[2015] 1 S.C.R.
by Chief Justice Stone and the other by Chagla,J. as he then
was.
Stone C.J.held:-
"In my judgment,reading the correspondenceas
awhole,it atnostagepassedfrom the meltingpot
of
negotiations to crystallizeas an agreement to extend the
timefor theperformance
of the contract. The attitude of
the purchaser throughoutthe correspondencewas:
"Satisfy us thatyouare doingyour best to obtainthe
goodsfrom yoursuppliersand
we will thenconsider
fixinga newdatefor delivery
of the goods to us". On the
otherhand the attitude
of thevendorsthroughoutthe
correspondencewas
to avoid the purchaser'sdemand
and
to simply say: "You knowthat we c;mnot effectdelivery
fromour suppliersand until
we do so we cannotdeliver
thegoodsto
you". There was never in my judgment
any consensusad-idem, no agreement,express or
implied, to extend the timeeither to any particulardate
or to the happening of some future event.Mere
forbearance
in myopinion to instituteproceedings or to
give notice of rescissioncannot be an extension ·or the
timefor
the performance of a contractwithin the meaning
of s. 63 of the Contract Act." (at 226 & 227)
Chagla, J. in a separatejudgmentheld:-
" Under s. 55 of the Indian Contract Act,the
promisee
is given the option to avoid the contractwhere
thepromisorfails
to perform the contractat thetimefixed
in the contract.It is open to the promiseenot to exercise
theoption
or to exercisethe optionat any time, butit is
clear
to mymindthat the promiseecannot by the mere
fact
of notexercising the optionchange or alter the date
of performancefixed under the contractitself Under s.
63 of the IndianContractAct, the promiseemay make
certain concessions to the promisor which are
advantageous to thepromisor,and one of themis that
hemayextendthe timefor suchperformance.But it is
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 64 7
AUTHORITY [R.F. NARIMAN, J.]
clearagainthat suchan extension of timecannotbe a A
unilateralextensionon the part of the promisee.It isonly
at therequest of thepromisorthat the promiseemay
agreeto extendthe time
of performanceand thereby
bringabout
an agreementfor extension of time. Therefore
itisonly
as a result of theoperation of s. 63 of the Indian B
Contract Act thatthe timefor theperformance of the
contractcan be extendedand thattimecan onlybe
extended by an agreement arrived at betweenthe
promisorand the
promisee." (at 229)
24.Theaforesaid judgment would apply in a situation
wherea promiseeaccedes to therequest
of thepromiserto
extendtime that is fixedfor hisownbenefit.Thus,
in Keshavlal
Lallubhai
Patel and Ors. v. LalbhaiTrikumlal Mills Ltd 1959
SCR 213, this Court held:-
"The truelegalposition in regard to the extension of time
fortheperformance
of a contractis quite clear under
s. 63 of theIndianContractAct. Everypromisee, as the
sectionprovides,
may extend time for theperformance
c
D
of the contract. The question as to howextension of time E
may be agreedupon by thepartieshas been the subject
matter of someargument at the Bar in the present
appeal.There can be no doubt, we think,that boththe
buyerand the sellermust agree
to extendtime for the
delivery
of goods.It wouldnot be open to thepromisee F
by hisunilateralact to extend the timefor performance
of his ownaccordfor hisown benefit."
25.However,such is notthepositionhere. In the present
case,the
appellant is thepromiserand ODA is thepromisee.
In sucha situation, ODA can certainlyunilaterally extend the timeG
forpaymentunder Section63
of the Contract Act as thetime
forpaymentis notfor DDA'sown benefitbut for thebenefit
of
the appellant. Thepresentcase would be coveredby two
judgments
of theSupremeCourt. In Citi Bank N.A. v. Standard
CharteredBank,
(2004) 1 SCC Page 12, thisCourt held: H
648 SUPREME COURT REPORTS [2015] 1 S.C.R.
A "50. Under Section 63, unlike Section 62, a
B
c
D
E
F
G
H
promiseecan act unilaterally af!d may
(i) dispensewith wholly or in part, or
(ii) remitwholly or in part,
the performance of the promisemade to him, or
(iii) mayextendthe timefor suchperformance, or
(iv) mayacceptinstead of it anysatisfactionwhich he
thinks
fit."
26. Similarly in S. Brahmanand v. K.R. Muthugopa/,
(2005) 12 SCC 764the Supreme Court held:
"34. Thus, this was a situationwhere the original
agreement of 10-3-1989 had a "fixed date" for
performance,but by thesubsequentletter of 18-6-1992
the
defendants madea request for postponing the
performance
to afuturedate withoutfixing any furtherdate
forperformance.
This was acceptedby theplaintiffsby
theiract
of forbearanceand not insisting on performance
forthwith.
There is nothingstrange in time for performance
beingextended,even thoughoriginallythe agreement
hada fixeddate.Section
63 of the ContractAct, 1872
providesthat everypromiseemay extendtime for the
performance
of thecontract. Such an agreementto
extendtime neednot necessarilybe reduced
to writing,
butmay
be provedby oralevidence or, in somecases,
even by evidence of conductincludingforbearance on
the part of theotherparty. [See in this connectionthe
observations of this Court in Keshavlal Lal/ubhai
Patel v. La/bhai TrikumlalMills Ltd.,1959 SCR 213: AIR
1958 SC 512, para 8. See a/so in this
connectionSaraswathamma v. H. Sharad Shrikhande,
AIR 2005 Kant 292 and K. VenkojiRao v. M. Abdul
Khuddur Kureshi, AIR 1991 Kant 119, followingthe
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 649
AUTHORITY [R.F. NARIMAN, J.]
judgment in KeshavlalLallubhai Patel (supra).] Thus, in A
this case there was a variationin thedate of performance
byexpressrepresentationby thedefendants,agreed
to
by theact of forbearanceon thepart of the plaintiffs.
What
was originallycovered by thefirstpart of Article 54,
nowfell withinthe purview of thesecqndpart of the
article.PazhaniappaChettiyar
v. South Indian Planting
andIndustrial
Co. Ltd. [AIR1953Trav Co 161] was a
similarinstancewhere the contractwhen initiallymade
hada datefixedfor theperformance
of the contractbut
B
the Court was of the view that "in the eventsthat c
happened in this case, the agreement in questionthough
started
with fixation of aperiodfor thecompletion of the
transactionbecame one withoutsuch period
on account
of the peculiar facts and circumstances already
explainedand the co~tract, therefore,became one in D
which no time was fixedfor its performance" andheldthat
what
was originallycovered bythe firstpart of Article113
of the Limitation Act, 1908 would fall under the second
part of the saidarticlebecause of the supervening
circumstances
of the case. "(at Page 777)
27.Coming to the application of Article 14, theDivision
Bench
in paragraph37 stated:-
E
"37. Now, in India,reasonableness in State action is a
facet
of Article 14 of theConstitution of Indiaand in the
field
of contractwould have a considerableplay at the
precontractstage.
Once parties have enteredinto a
contractualobligation, they would be bound by the
contractand the onlyreasonablenesswould
be of the
kindenvisagedby the
Supreme Courtin thedecision G
reported as AIR1963 SC 1144 T.P. Oaver v. Lodge
Vict6riaNo.363
SC Belgaum & Ors. On the subject of a
member
of aclubbeingexpelled,and the relationship
being
a contract as per therulesand regulations of the
club,adherencewhereto
was agreed to byhewho
F
H
650 SUPREME COURT REPORTS[2015] 1 S.C.R.
A became a member of the cluband the management of
the club,the SupremeCourt observedthat in such private
affairs,it wouldbe goodfaith
in taking an actionwhich is
rootedin theminds
of modernmen and women i.e. in a
moderndemocraticsociety and no more.The decision
B guidesthat where a privateaffair i.e. a contractis so
pervertedby
a party that it offendsthe concept of a fair
play
in a modernsociety,alone then can the action l)e
questioned as not in goodfaith and sufficewould it be to
statethat anythingdone not in goodfaith wouldbe
c unreasonably done."
28. It will benoticedat oncethat T.P. Daver v. Lodge
Victoria
No.363, S.C.Belgaum, 1964(1) SCR 1, is notan
authority
on Article 14 at all. It deals with clubs andthe factthat
rules or bye-laws whichbind members of such clubs haveto
Dbe strictlyadheredto.
On the otherhand in ABL International
Ltd. v. ExportCredit Guarantee Corpn. of India Ltd., (2004) 3
SCC 553 at paras22 and23, the Supreme Court held:
E
F
GH
"22. Wedo not think the above judgment in Y.ST
Industries Ltd. {(2001) 1 sec 298: 2001 sec (L&S)227]
supportsthe argument
of the learnedcounselon the
question
of maintainability of thepresentwrit petition.It
is to be notedthat VST IndustriesLtd.{(2001)1 SCC 298
:
2001 sec (L&S)227] againstwhom the writpetitionwas
filedwasnot
a State or an instrumentality of a State as
contemplatedunder Article 12 of the Constitution,hence,
in the normalcourse,no writcouldhave beenissued
againstthe saidindustry.But it wasthe contention
of the
writpetitionerin thatcasethat the saidindustrywas
obligatedunder the statuteconcerned
to performcertain
publicfunctions;failure
to do sowouldgive rise to a
complaintunder Article226 against a privatebody. While
cpnsideringsuch argument,this Courtheld that when
an
authorityhas to perform a public function or a publicduty,
if there is a failurea writpetitionunder Article226 of the
KAILASH NATH ASSOCIATES v. DELHI DEVELOPMENT 651
AUTHORITY [R.F. NARIMAN,J.]
Constitutionis maintainable. In theinstantcase, as to the A
fact thatthe respondentis an instrumentality of a State,
there is nodispute but thequestionis: wasthe first
respondentdischarging
a public duty or a publicfunction
whilerepudiatingthe claim
of theappellantsarising out
of a contract?Answer to this question, in our opinion,is B
found in the judgment of this Court in the case of Kumari
ShrilekhaVidyarthi
v. State of U. P. [(1991) 1 SCC 212 :
1991 SCC (L&S) 742]whereinthis Courtheld: (SCC pp.
236-37, paras 22 & 24)
"The impact of every State actionis also on public C
interest.. .. It is really the nature of its personality
as State whichis significantand mustcharacterize
allitsactions,
in whateverfield, and not the nature
of function,contractual or otherwise,which is
decisive
of thenature of scrutinypermittedfor D
examining the validity of its act. The requirement
of Article 14 being the duty to act fairly,justlyand
reasonably,there is
nothing which militates
againstthe concept of requiringthe State always
to so act, even in contractual matters." E
23. It is clear from the aboveobservations of this Court,
once the State or an instrumentality of the State is a party
of the contract,it hasan obligation in law to actfairly,
justlyand reasonablywhich is therequirement
of Article F
14 of theConstitution of India.Therefore, if by the
impugnedrepudiation
of the claim of theappellants the
firstrespondentas aninstrumentality of the State has
acted
in contravention of theabovesaidrequirement of
Article 14, then we have no hesitation in holdingthat a G
writ courtcan issuesuitabledirections to set rightthe
arbitraryactions
of the first respondent"
29.Basedon thefactsof thiscase,it would be arbitrary
forthe
DOA to forfeitthe earnestmoney on twofundamental
grounds.First, thereis
no breachof contracton thepartof theH
652 SUPREME COURT REPORTS (2015] 1 S.C.R.
A
appellC_nt as has been held above.And second, ODA not
having "been put to any loss, even if ODAcould insiston a
contractualstipulation in its favour,it would be arbitraryto allow
DOA as a publiq authority to appropriate Rs.78,00,000/
(RupeesSeventy Eight Lakhs)withoutany loss being caused.
B
It is clear, therefore,that Article 14 would apply in the field of
contract in this caseand the finding oqhe DivisionBench on
c
D
E
F
Gthis
aspectis herebyreversed.
,.
30. We now cometo thereasoningwhich involves Section
74
of theContractAct. TheDivisionBench held:
"38. The learned Single Judgehas heldthat the property
was ultimatelyauctioned in the year 1994 at a pricewhich
fetched
DOA ahandsomereturn of Rupees 11. 78 crores
andtherebeingno damagessuffered
by ODA, it could
notforfeitthe earnestmoney.
39. The said viewruns in the teeth of thedecision of the
Supreme Courtreportedas AIR 1970 SC 1986 Shree
· HanumanCotton Mills. & Anr. V. Tata Aircraft Ltd. which
holdsthat as againstan amounttendered
by way of
security,amount tenderedas earnestmoney could be
forfeitedas perterms
of the contract.
40. We mayadditionallyobserve that originaltime to pay
the balancebid consideration,as per Ex.P-1 was May 18,
1982 and as extended by Ex. P-8 wasOctober 28, 1982.
That DOA couldauctionthe plot in theyear 1994 in the
sum
of Rupees 11.78 crorewas immaterial and not
relevantevidencefor thereasondamageswith respect
tothe
price of property haveto be computed with
reference
to thedate of thebreach of the contract."
31.Section74 as it originally. stoodread thus:
"When a contracthas beenbroken, if a sumis named in
thecontractas theamount to be paid in case of such
H breach,the partycomplaining of the breachis entitled,
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 653
AUTHORITY [R.F. NARIMAN, J.]
whether or not actualdamage or loss is proved to have A
beencausedthereby, to receivefrom the partywho has
broken the contract reasona~ble compensation not
exceedingthe amountso named."
32. By an amendment made in .1899,the Section was 8
amendedto read:
"74. Compensationfor breach of contractwhere penalty
stipulated
for. - When a contracthas beenbroken, if a
sum is named in the contractas theamount to be paid
in case of suchbreach,or if the contractcontainsany C
other stipulationby way of penalty,the partycomplaining
of the breach is entitled,whether or not actualdamage
or loss is proved to ilave been caused thereby,to
receivefrom the
party who has brokenthe contract
reasonablecompensationnot exceedingthe amountso
D
named or, as thecasemay be, the penaltystipulated for.
Explanation.-A stipulationfor increasedinterest from
thedate
of defaultmay be a stipulationby way of penalty.
Exception.-When anypersonenters into any bail-bond,
recognizance
or otherinstrument of the samenature, or,
underthe provisions of any law, or underthe orders of
theCentralGovernment or of any State Government,
givesany bondfor theperformance
of anypublicduty
or act in whichthe publicare interested,he shallbe
liable,
upon breach of any condition of any such
instrument, to pay thewholesum mentionedtherein.
E
F
Explanation.-A person who entersinto a contractwith
Governmentdoes not necessarilythereby undertakeany
G
public duty, or promise to do an actin whichthe public
are
interested."
33.Section 74 occurs in Chapter6 of the Indian Contract
Act,1872whichreads
"Of the consequences of breach of
contract".It is in fact sandwichedbetween Sections73 and75 H
654 SUPREME COURT REPORTS [2015] 1 S.C.R.
A which deal with compensationfor loss or damage caused by
breach
of contractand compensationfor damagewhich a party
maysustainthrough
non-fulfillment of a contractafter suchparty
rightfullyrescinds such contract.
It is importantto notethat like
Sections73 and75, compensationis payable for breach of
B contractunder Section74 only where damageor loss is caused
bysuchbreach.
·
34. In FatehChand v. Balkishan Oas, 1964 SCR (1) 515,
thisCourt
held:
C "The section is clearly an attempt to eliminate the
somewhatelaborate refinementsmade underthe English
common
law in distinguishing between stipulations
providing for payment of liquidated damages and
stipulations in thenature of penalty. Under thecommon
D /awa genuine pre-estimate of damages by mutual
agreement is regarded as a stipulationnaming liquidated
damagesand bindingbetweenthe parties:a stipulation
ina contractin terrorem
is a penalty andthe Court
refuses
to enforce it, awarding to theaggrievedparty only
E reasonablecompensation. The Indian Legislaturehas
sought
to cutacrossthe web of rulesand presumptions
underthe Englishcommon
law, by enactinga uniform
principleapplicable
to all stipulationsnaming amounts
to be paid in case of breach,and stipulationsby way of
F penalty.
Section 7 4 of the IndianContractAct dealswith the
measure
of damages in twoclasses of cases (i) where
G the contractnames a sum to be paid in case of breach
and
(ii) wherethe contractcontainsany otherstipulation
by way of penalty. We are in the present case not
concerned to decidewhethera covenant of forfeiture of
depositfor dueperformance of a contractfalls withinthe
H first class.The measure of damagesin the case of
KAI LASH NATH ASSOCIATES v. DELHI DEVELOPMENT 655
AUTHORITY [R.F. NARIMAN, J.]
breach of a stipulation by way of penalty is by A
Section 74 reasonablecompensationnot exceedingthe
penaltystipulated
for. In assessingdamages the Court
has,
subject tothe limit of the penalty stipulated,
jurisdiction to awardsuch compensation as it deems
reasonablehaving regard
to all thecircumstances of the
case.Jurisdiction
of the Court to awardcompensationin
case