Land Acquisition Act, 1894 – Land Acquisition, Rehabilitation
and Resettlement Act, 2013 – The High Court allowed the writ
petition filed by the Respondent Nos. 1 to 6 herein (original
petitioners) and directed the Appellant herein to pay the
requisite amount towards compensation as determined in the
Supplementary Award dated 02.05.2022 passed by the Land
Acquisition Collector (LAC) (Respondent No. 10) in the first
instance with liberty to recover the same from JAL (Respondent
No. 11) if permissible under the legal relationship between the
two companies – Correctness:
Held: An analysis of the Scheme agreed between the Appellant
and JAL is the key to determine who should pay the amount
determined under the Supplementary Award dated 02.05.2022 –
Clause 1.1 (o) defines the “Effective Date” as the date on which
the Scheme becomes effective in accordance with its terms, which
shall be the Closing Date [defined in Clause 1.1(k) and Clause 10.1] – The said date was decided to be 29.06.2017 among the
parties – The parties by way of Clause 1.1(w)(ix) agreed that all
litigations pertaining to the business and assets being transferred
to the Appellant that arose before or on the Closing Date would not
be transferred to the Appellant and will remain with JAL – Clause
7.1 of the Scheme states without any ambiguity that any legal
or other proceeding by or against JAL or its unit operating the
cement project relating to the JAL Business as defined in Clause
1.1(w), initiated on or arising and pending before the Effective
Date shall remain with JAL – The facts indicate that the land
acquisition proceedings had commenced before the Effective Date
of the Scheme (i.e. 29.06.2017) and the compensation remained
undetermined as on the Effective Date – These facts attract
the application of Clause 7.1 of the Scheme as the acquisition
proceedings and the liability to pay compensation associated with it
squarely falls within the meaning of ‘other proceedings’ as intended
by the parties under the said Clause – JAL has also not disputed
that it had made payment of the amount determined under the
Award of 2018 i.e., Rs. 10,77,53,842/- after the Effective Date of
the Scheme – The said amount has already been disbursed to
the landowners – After the LAC determined the amount under the
Award dated 08.06.2018, JAL paid the same without any protest
or reference to the Scheme – Therefore, at the stage of the
Supplementary Award pertaining to the same land and same
original landowners, JAL cannot be allowed to take the plea that
the payments with respect to the subject land were required to be
made by the Appellant. [Paras 21, 22, 24, 26, 27, 28, 29]
Land Acquisition, Rehabilitation and Resettlement Act,
2013 – s.101 – It is the case of JAL that the substantial delay
in acquisition of the subject land has frustrated its purpose,
and it could not make any use of the land – It was submitted
that if the Appellant does not require the said land, then it
should be returned to the original landowners and the amount
of Rs. 10,77,53,842/- paid under the Award of 2018 should be
refunded to JAL:
Held: The necessary conditions for the application of Section
101 are: (1) the land should be unutilized; and (2) the period it
remains not in use should be at least five years from the date
of taking of possession – There is no merit in the contention
of JAL that the land be returned to the original landowners – While period of five years has elapsed from the date of taking of
possession by JAL, the first condition that the land should remain
unutilized is not fulfilled – The subject land was acquired for the
purpose of providing a safety zone to the mining area of the
cement plant – No other use except that the subject land may
pose hazard to the residents was envisaged during the acquisition
proceedings – JAL cannot pray for return of the land as that
would result in endangering the lives and property of the original
landowners – It is also found that the subject land has been in
use all throughout the operation of the cement project by serving
as a safety zone and the condition of being unutilized is not
satisfied – It is not in dispute that the Supplementary Award had
to be passed as the compensation for standing crops, structures
and other damages for the subject land which could not be fixed
and evaluated under the Award No. 1 dated 08.06.2018 – The
passing of Supplementary Award was not a fresh exercise but rather
a continuation/extension of the Award of 2018 – Therefore, when
JAL has already paid the compensation amount as determined
under the previous Award without any demur, it cannot be allowed
to question its liability under the Supplementary Award and make
a plea for return of the land at this stage on the ground that
the purpose of the land is frustrated due to delay in acquisition
proceedings. [Paras 35, 36, 37, 38, 39]
Land Acquisition, Rehabilitation and Resettlement Act, 2013 –
s.101 – Scope of:
Held: The instant section was introduced in the 2013 Act for
the first time as a beneficial provision for the landowners whose
lands were usurped but remained unutilized or were not used
in accordance with the purpose stated in the notifications under
Section 4 – However, the application of the Section is warranted
only in the circumstances where the return of the land would
benefit the landowners – The party which has failed to utilize the
land cannot plead for the return of the land and consequent refund
of the compensation paid, as that would tantamount to taking
advantage of its own wrong or default. [Para 40]
Constitution of India – Art.300-A – Role of the State under
Article 300-A of the Constitution – Responsibility of State to
ensure full payment of compensation determined:
Held: It is settled that once the compensation has been determined,
the same is payable immediately without any requirement of a representation or request by the landowners and a duty is cast on
the State to pay such compensation to the land losers, otherwise
there would be a breach of Article 300-A of the Constitution – In the
instant case, the Government of Himachal Pradesh as a welfare
State ought to have proactively intervened in the matter with a view
to ensure that the requisite amount towards compensation is paid
at the earliest – The State cannot abdicate its constitutional and
statutory responsibility of payment of compensation by arguing that
its role was limited to initiating acquisition proceedings under the
MOU signed between the Appellant, JAL and itself – This Court finds
that the delay in the payment of compensation to the landowners
after taking away ownership of the subject land from them is in
contravention to the spirit of the constitutional scheme of Article
300A and the idea of a welfare State – The State Government,
in peculiar circumstances, was expected to make the requisite
payment towards compensation to the landowners from its own
treasury and should have thereafter proceeded to recover the
same from JAL – Instead of making the poor landowners to run
after the powerful corporate houses, it should have compelled JAL
to make the necessary payment – Also, the State of Himachal
Pradesh, being a welfare state, did not ensure payment of
compensation to the Respondent Nos. 1-6 before taking possession
of their land – A bare reading of Section 38 of the 2013 Act
indicates that the payment of full and final compensation to the
land owners is a precursor to taking possession of the land sought
to be acquired from such persons – In fact, the landowners had
to approach the High Court to seek directions to the LAC for
passing of the supplementary award which was finally passed on
02.05.2022 that is, after a period of almost four years from the date
of passing of the Award of 2018 – Further, Section 41 of 1894 Act
necessitates an agreement between the appropriate government
and the company for whose purpose the land is being acquired –
One of the purposes of such an agreement is to ensure that
payment towards the cost of acquisition is made by the company
to the appropriate government and it is only upon such payment
that the land is transferred to the company – Thus, it can be said
that JAL was mandated to make the requisite payment to the State
of Himachal Pradesh prior to the subject land being transferred
to it – However, even before the amount of compensation could
be determined by way of a supplementary award as stipulated in
the Award dated 08.06.2018, the subject land stood transferred to JAL – This is in contravention of Section 38 of the 2013 Act and
Section 41 of the 1894 Act respectively – Thus, the Respondent
Nos. 7 (State of Himachal Pradesh) and 10 (LAC) are directed
to pay the compensation amount of Rs. 3,05,31,095/- – The total
amount paid by the State shall be recovered from the Respondent
No. 11 (JAL). [Paras 47, 48, 50, 52, 54, 55, 58]